8 Road Construction Projects Planned for SLC in 2018

 Pavement preservation projects:

·         1200 East - from 600 South to 800 South:

This project is scheduled for the summer of 2018 and is estimated to cost $500,000. Crews will install a raised median and resurface the road to prolong its longevity.

·         1500 East - from 900 South to 1300 South

·         1700 South - from 1700 East to 1900 East

·         2100 East - from 1700 South to Parkway 

Avenue Road reconstruction projects

·         Genesee Avenue - from 900 West to 1000 West

·         Simpson Avenue - from Wyoming Street to Broadmoor Street

·         Wilmington Avenue - from 2000 East to 2100 East

·         Gladiola Street - from 500 South to 900 South: This project is scheduled from June to November 2018 and is estimated to cost $3 million. Crews will reconstruct the road segment with new concrete pavement that’s built to last about 50 years and to withstand heavy trucks that travel through the industrial district.